| 1. Name of the Growth Centre |
: |
KOZHIKODE |
| 2. Block/District/State |
: |
Balussery Block, Kozhikode District, Kerala State |
| 3. Name of the implementing agency |
: |
Kerala State Industrial DevelopmentCorporation Ltd. |
| 4. Approved Cost |
: |
Rs.30 Crores |
| 5. Extent of land proposed to be acquired |
: |
308 Acres |
| 6. Present Status of land |
|
|
(a) If in the process of acquisitionindicate the present stage and the : The entire land is in possession. likely date of acquisition. |
: |
The entire land is in possession. |
| (b) If acquired, give full details |
: |
Acquired 308 acres at Kinalur, Balussery, Kozhikode. Out of this 100 acres developed. |
| 7. No. of plots developed and allotted |
: |
51 Nos. plots have been developed and steps for allotment are being undertaken. |
8. No. of sheds/flatted factories constructed |
: |
1. One Industrial Tower Block with an area of 3888 sq.metres has been completed.
2. An Administrative Building with an area of 1964 sq.metres has been completed. |
| 9. No. of plots occupied |
: |
The application for allotment are being processed. |
| 10. No. of sheds occupied |
: |
Nil. |
| 11. Roads constructed within the Growth Centre (in Kms.) |
: |
Construction of internal roads for a length of 2.98Km completed. |
| 12. Approach roads to Highway (in Kms.) |
: |
Land acquisition for widening the road is in progress and the State Govt. is taking steps to widen and strengthen the road. Widening and strengthening of approach road are in progress. |
| 13. Water Supply facilities: |
|
|
| (a) Industrial |
: |
Construction of overhead water tank is completed. Construction of water treat-ment plant is completed. Internal elec-trificatilon of Water Treatment Plant works have started and is nearing completion. Construction of RCC pond pump house and Ancillary works completed. |
| (b) Domestic |
: |
Installation of Six Bore wells has been completed. |
| 14. Drainage facilities/effluent system |
: |
Schemes have been finalized and sewage pipe line laid. |
15. Setting up of power within the Growth Centre |
: |
KSEB has allocated 630 KVA power and sub station work is completed. Steps are being taken to obtain approval of KSEB. |
16. Status of distribution power within the Growth Centre to – |
: |
Consultancy arranged. Survey and preparation of detailed estimate completed. Work is in tendering stage. |
| (a) The Industrial Units |
: |
A sub-station shall be constructed for 10 MVA, KSEB power. |
| (b) Street lights |
: |
110KV/11KV sub-station and street lighting job shall be undertaken immediately. Work is in tendering stage. The above work cannot be taken up now due to paucity of fund. |
| (c) Domestic Electricity Supply |
: |
11 KV Sub station work has been completed and domestic electricity supply will be available soon according to necessity. |
| 17. Status of Telecom facilities |
: |
3 telephone connections have already been installed in Administrative block. |
| 18. Development of residential areas |
: |
About 10 acres of land is earmarked for residential purpose. |