Growth Centres - FACILITIES AT IGC, MALAPPURAM
1. Name of the Growth Centre : ALAPPUZHA – MALAPPURAM
2. Block/District/State :

Malappuram, Malappuram District, Kerala State.

3. Name of the implementing agency :

Kerala State Industrial Development
Corporation Limited.

4. Approved Cost : Rs.35 Crores.
5. Extent of land proposed to be acquired : 258 Acres.
6. Present Status of land    

(a) If in the process of acquisition indicate the present stage and the likely date of acquisition.

: The land has been taken over.

(b) If acquired, give full details

:

Acquired about 258 acres of land.

7. No. of plots developed and allotted

:

55 Nos. of Plots are developed and allotment based on requests for land is being attended to.

8. No. of sheds/flatted factories constructed

:

One Administrative and Canteen Building completed. Detailed estimate of SDF building is under preparation. Detailed estimate for providing fencing at essential portions in the IGC boundary and construction of gates and security cabin completed. Work tendered. Tender finalized and agreement executed. Work is in progress.

9. No. of plots occupied : Nil.
10. No. of sheds occupied : Nil.

11. Roads constructed within the Growth Centre (in Kms.)

:

3.56 Km. internal road upto mettalling Providing 20mm chipping carpet for 3.56 Km internal road completed.

12. Approach roads to Highway (in Kms.)

:

Work is nearing completion. There is existing approach road from High way to IGC.

13. Water Supply facilities:    
(a) Industrial :

1. Industrial water supply arrangements shall be made by constructing suitable pond, within or nearby IGC land. Ground water investigation arranged to assess the possibility of providing water supply scheme utilizing ground water. Ground water investigation work completed.
2. Water Supply Scheme for Administrative Block building completed.
3. Providing Water Supply Scheme for existing Administrative Block Building from bore well, work tendered. Tender finalized and agreement executed. Work is in progress.

(b) Domestic :

Five Bore wells have been installed.

14. Drainage facilities/effluent system

:

Shall be undertaken as per master plan.

15. Setting up of power within the Growth Centre.

:

Construction of a Sub-station for 630 KVA is completed. Power connection is awaited.

16. Status of distribution power within the Growth Centre to -

:

Consultancy arranged. Site survey and preparation of detailed estimate completed. Work is in tendering stage.

(a) The Industrial Units :

Arrangements for 10 MVA power from KSEB is being arranged. Steps are being taken for obtaining approval of KSEB. Electrification works to Administrative building is completed.

(b) Street lights :

110 KV/11KV sub-station and street light work is in tendering stage. This work cannot be taken up now due to paucity of fund.

(c) Domestic Electricity Supply :

KSEB has allotted 630 KVA power and the substation work is complete. Domestic Electricity supply shall be made available soon according to necessity.

17. Status of Telecom facilities : Kept in abeyance.
18. Development of residential areas :

About 10 acres of land is earmarked for residential purpose.

     
 